Dear Rupesh
look i was facing the same challenge that the Project Manager need 3 Month Look-ahead
let me define the lookahed report - It's to show the
1- activity starts at Certain period range and also
2- activities that already "Work In Progress "
Example :- Let's say i wanna make Lookahed report for period " 1/8/2015 - 1/10/2015"
I'm Using the planning board plan ----> filter --> select conditions as following :-
1- Earl Sched Start B + Use Multiple Selection + "Exclude" the single value + Enter the Period Finish date "01/10/2015"
2- Earl Sched Finish B + Use Multiple Selection + "Exclude" the single value + Enter the period Start date "01/08/2015"
it will work with you