Dear Tanweer

 

look i was facing the same challenge that the Project Manager need 3 Month Look-ahead

let me define the lookahed report - It's to show the

1- activity starts at Certain period range and also

2- activities that already "Work In Progress "

 

Example :- Let's say i wanna make Lookahed report for period " 1/8/2015 - 1/10/2015"


I'm Using the planning board plan ----> filter --> select conditions as following :-

1- Earl Sched Start B  + Use Multiple Selection + "Exclude" the single value + Enter the Period Finish date  "01/10/2015"

2- Earl Sched Finish B + Use Multiple Selection + "Exclude" the single value + Enter the period Start date "01/08/2015"

 

it will work with you

 