Hi Meesha,
There are two types of returns, in the project and from the project.
But when you do changes in the project it is the same as changing the original budget, except that it will be documented with a separate budget document through return.
So, if you need a simple budget change that does not need own document, just change the budget with CJ30.
Regards,
Paulo