Hello,
In ME if shop order is downloaded from ECC and it has been released also sfc are started. Does it allow routing changes through ECC?
In ECC if we try to update routing in shop order using CO02 transaction, it will not allow to directly make changes.
But in ECC we can do the changes using Order change management(OCM), it allows to make routing changes
then we can update the shop order with new routing change through CO02.
But trying to download the updated shop order in ME is getting failed (MEINT its get failed)
Is it possible to directly download the updated shop order with routing changes in SAP ME if shop order is already released? or
Change production is the only way to attach new routing if shop order is already released.
Thanks in advance
Regards,
Kshitiz