Re: MRP for Sales Requirements using PD

$
0
0

Hello,

 

You can do that with planning Horizon = RLT

In MD02 use processing key NETPL ;- Net change planning in the planning horizon

And maintain the planning horizon in OPPQ or MRP group OPPR

For example if we set planning horizon as 30 days = RLT

 

Run The MRP and check the results MRP will plan the sales order within planning Horizon

 

Best Regards,

R.Brahmankar