Hi experts
At the time of SO creation in VA01 I am doing costing by selecting extra and clicking on costing. It is triggering cost as per variant defined in Req class. But prob is, the cost of routing is not calculating if I give sales order qty less than my routing base qty and if I give more than base qty it takes hours for base qty mentioned in routing. But if I give same qty in sales order it takes right operation hours.
But BOM qty always changing as per sales qty while cost is calculating.
Example:
Routing operation Base qty 1000 Activity hrs 1000 Lot size in mat master 1000 units
If I give sales qty 1000 units no issue
If I give sales qty 900 units no activity cost in sales order costing
If I give sales qty 1200 units it takes cost of 1000 units only ie 1000 hrs
How can be solved?