Hi Maria,
thanks for reply,
My problem is i have budget for project over all is 300.
i am going to distribute budget for WBS 1 is 100
WBS 2 is 100
WBS 3 is 100
Then i am going to book the cost(MM,FI) wbs 1 element is 140, it has to be allow the cost, because i have provide the budget for project overall is 300, i want check budget project level only not for wbs element wise. this is my client requirement.