Re: Forward scheduling

$
0
0

Hi SR,

 

"Material Constrained Planning' is only available in SAP APO..

 

In ECC ,  you can achieve above by setting Planning time Fence for FG = 'Total Repl. Lead time'   of MRP3.  You also need to change MRP type to P1.

 

Note that 'Total Repl lead time' is longest production path(Critical path) across all BOM level & not calculated by SAP , it should be calculated outside SAP using some simulation tool & input in SAP.

 

Hope it helps,Jatin